Friday, June 1, 2012

Week 9

Accomplishments for this week:

-Completed waterproofing box for motor, installed motor.
Meet the new box. (Same as the old box.)


-Installed rotating pipe and attached motors.
Assembly nearing completion.

-Largely completed wiring.
-Assembled most of the ROV
Motors have since been attached.

-Completed designs for sprockets for the chain.
8-tooth gear for drive beam.

40-tooth gear for motor beam.


-Began to put together final presentation.

Goals for next week:
-Finish control box.
-Finish assembling and test the ROV.

No comments: